Artesis e-MCM Pilot in 90 Days: Step-by-Step Rollout Plan for Industrial Sites
Launch an e-MCM pilot in three months: asset selection, install, self-learning, alarm verification and scale-up decision — checklist for reliability engineers in Kazakhstan.

Full-fleet Artesis e-MCM rollout takes a year. Proof of value fits in 90 days: 3–5 critical drives, measurable lead time, management-ready report.
Success KPIs
| KPI | 90-day target |
|---|---|
| Confirmed real faults | ≥ 1 |
| Lead time (alarm → repair) | ≥ 14 days |
| False alarms | < 20% |
| Prevented downtime | ≥ 1 documented |
| Scale-up decision | Yes/no with ROI |
Asset selection is critical — without one confirmed early find, the pilot is hard to defend.
Weeks 1–2: preparation
Pick 3–5 motors
Score on: criticality, failure history, MCC access, variety (pump/fan/conveyor), maintenance logs.
Examples → industry map, mills, fans, submersible pumps.
Team
| Role | Task |
|---|---|
| Reliability engineer | Owner, alarm review |
| Electrical lead | MCC access, CT install |
| Area mechanic | On-machine verification |
| KEG TRK | Supply, commissioning, training |
Before start
- Single-line diagrams
- Motor nameplates (kW, RPM, DOL/VFD)
- 24-month failure history
- Existing vibration/thermography baseline if any
Weeks 3–4: install and self-learning
Install (1–2 h per motor): unit in panel, CTs + voltage, network, nameplate data in software.
Self-learning (7–21 days): normal load ranges, multiple VFD speeds if applicable. Do not treat yellow flags as emergencies during learning — log process upsets.
Weeks 5–8: operation and verification
Weekly ritual (30 min)
- Dashboard / Artesis IoT
- Traffic-light status
- New alarms — severity, time-to-failure
- Schedule site visit for amber/red
On-machine checks
| e-MCM indication | Field check |
|---|---|
| Bearing | SDT ultrasound, SCOUT vibration |
| Misalignment | Laser alignment |
| Pump cavitation | Pressure, process mode |
| Electrical | Terminal thermography |
Pilot log (mandatory)
Date | Asset | Alarm | Action | Result | Lead time
Basis for management report and ROI (downtime cost).
Weeks 9–12: report and scale
Report structure
- Executive summary
- Why these assets
- Event table
- Confirmed finds with evidence
- False alarms and tuning
- ROI
- 12-month roadmap
Typical next steps
| Outcome | Next step |
|---|---|
| ≥2 confirmed faults | +10–20 e-MCM in year 1 |
| 1 fault, good lead time | +5 on class A |
| Mostly false alarms | Tune, extend 30 days |
| No events | Move to chronic assets |
Parallel: AMT Pro
While e-MCM learns on 5 points, AMT Pro can survey the whole fleet — route guide.
Common mistakes
- Too many pilot points — start with 3.
- No data owner — no weekly review.
- Wrong VFD setting in software.
- No field verification.
- No management report — no budget for scale.
Summary
90 days is enough for full cycle: install → learn → real alarms → confirmed repair → ROI. KEG TRK supports turnkey pilots: asset pick, install, training, report template.
→ Three-tier strategy · Motor monitoring intro · e-PCM for DGS
Equipment in this article
Artesis e-MCM — Online Sensorless Motor Monitoring
Online sensorless electric motor monitoring with AI and digital twin
Artesis AMT Pro — Portable Electric Motor Tester
Portable sensorless motor diagnostics with AI analysis — full test in 7 minutes
Artesis IoT — Cloud Monitoring Platform
Cloud platform for monitoring data management, analytics and reporting
Read also
8/24/2026
Why Artesis Omnisight Is a Revolutionary Solution for Predictive Maintenance
Most condition monitoring programs split assets into "critical" and "everything else" with incompatible tools and no shared data model. Artesis Omnisight collapses that split at the signal level — here is how and why it works.
6/30/2026
Three-Tier Artesis PdM: AMT Pro → e-MCM/e-PCM → IoT
Build predictive maintenance without a big-bang project: AMT Pro route on the full fleet, online on critical assets, IoT for multi-site corporate reporting.
6/30/2026
Route-Based Motor Diagnostics with Artesis AMT Pro: 50 Machines per Shift
Build a predictive route with portable AMT Pro: 7-minute tests, automatic reports, and how it fits with e-MCM online monitoring on Kazakhstan plants.